The project must be linked to the ERP as well as a Project Manager and Design Professional provided in the Project Team table.
The Prime Contract must be entered and Approved.
The project budget must be entered and linked to the ERP.
To issue commitments in Procore the recipient (Vendor) must be listed in the Directory, linked to the ERP as indicated by Vendor ID number and green tag immediately to the right of the vendor name.
In addition, a contact person and invoice contact must be listed for the Vendor.
Determine proper settings based on the prime contract requirements. By default, the following are checked.
PURCHASE ORDERS
KBDG Naming Convention: “PO” followed by the Job No then sequence (PO-18999-001)
- Make this visible to only administrators and the following users. Place a checkmark in this box to limit the visibility of the purchase order to users with ‘Admin’ on the Commitments tool and users specified in the Select a Person drop-down list.
- Allow these users to see SOV items. Place a checkmark in this box to limit the visibility of the Schedule of Values (SOV) items on the purchase order to users with ‘Admin’ on the Commitments tool and users specified in the Select a Person drop-down list.
- Select a Person. Select one or more people from the list. You can allow non-Admin level users to view the Purchase Order, if desired. Additionally, you can allow selected non-Admin users to have read-only access to the to individual line items under the SOV subtab.
Purchase Orders do not typically require Bonds. If this is the case, consult with Risk Management on how to best handle incorporating into this Commitment.
Navigate to the Purchase Order to be modified then click the Schedule of Values tab. In the new page click the Edit button to begin creating the Schedule of Values.
Enter the information into the fields.
Click +Add and add additional line items as needed.
Save the Purchase Order when complete.
If using DocuSign, navigate to the General subtab, click Edit then Complete with DocuSign and follow the prompts.
EXPORT TO PDF
If not using DocuSign, export the Purchase Order by navigating to the General subtab, click Export then select PDF. The approved KBDG Purchase Order will be generated in a new tab suitable for saving, printing, etc.
SEND TO ERP
Once executed, update the status to Approved, check the box to mark as Executed, then click Save. Finally, click Send to ERP. If using DocuSign, the status will update automatically.
The accounting approver must take steps to accept the commitment for the sync to begin. Upon doing so the PO will be visible in both systems after the synchronization has completed, usually within a couple of minutes.
SUBCONTRACTS
KBDG Naming Convention: “SC” followed by the Job No then sequence (SC-18999-001).
At a minimum, all Long Form subcontracts shall have the following attachments:
- Exhibit A – The Subcontract Work
- Exhibit B – Drawings, Specifications, General and Other Conditions
- Exhibit C – Project Schedule
Upon execution, verify the inclusions in this field are identical to those of the executed agreement.
IT IS NOT NECESSARY TO ATTACH A SEPARATE SCOPE OF WORK FOR SHORT FORM OR PSA CONTRACTS AS THE INFORMATION ENTERED IN THIS FIELD IS INCLUDED WHEN THE CONTRACT IS GENERATED INTO A PDF OR THRU DOCUSIGN.
If “Are Required” is selected, the applicable exhibits will be included in the Long Form subcontract automatically.
Clarify these modified payment terms in the Scope of Work and Inclusions field.
Navigate to the Purchase Order to be modified then click the Schedule of Values tab. In the new page click the Edit button to begin creating the Schedule of Values.
Enter the information into the fields.
THE DESCRIPTION MUST BE LESS THAN OR EQUAL TO 60 CHARACTERS IN LENGTH OTHERWISE IT WILL NOT SAVE.
Click +Add and add additional line items as needed.
Click Save when complete.
If using DocuSign, navigate to the General subtab, click Edit then Complete with DocuSign. Follow the prompts. *Requires a DocuSign license.
Prior to export, ensure that the status has been updated to accurately reflect the cost in the project budget. A status with Out For Signature will be appear in the Pending Cost column while Approved or Completed will appear in the Committed Cost column.
DOCUSIGN
Only current licensees can send documents through DocuSign. Utilizing this service greatly improves the efficiency in which teams can send, sign, and retrieve documents. It is strongly encouraged for all projects and vendors to use this service. CLICK HERE TO LEARN MORE
EXPORT TO PDF
If not using DocuSign, export the Subcontract by navigating to the General subtab, click Export then select PDF. The approved KBDG Subcontract will be generated in a new tab suitable for saving, printing, etc.
SEND TO ERP
Once executed, update the status to Approved, check the box to mark as Executed, click Save then click Send to ERP.
The accounting approver must take steps to accept the commitment for the sync to begin. Upon doing so the Subcontract will be visible in both systems after the synchronization has completed, usually within a couple of minutes.