KBD Group delivered exceptional design-build services for a climate-controlled storage area within an active UPS facility operating 24/7.
Toyo Tire Mixer #15
KBD Group is providing general contracting services for a new mixing tower for tandem mixer # 15.
Burg Vinegar Jefferson
KBD Group provided design-build services for Burg Vinegar Jefferson, for a approximately 15,000 SF state-of-the-art manufacturing facility.
Kobayashi Building Expansion
KBD Group provided design-build services for Kobayashi Expansion, a 160,000 SF expansion, executed in three comprehensive phases.
Ajin Georgia
KBD Group worked as the design-builder for Joon Georgia, a subsidiary of Ajin USA, brand-new manufacturing plant in Statesboro, GA.
Stonemont Braselton
KBD Group provided general contracting services for Stonemont Braselton, a 234,133 SF speculative warehouse facility.
Savannah Main Gate
KBD Group is providing general contracting services for two building packages of speculative warehouses totaling 545,521 SF
Vitesco Expansion
KBD Group provided General Contracting services for this 40,000 SF expansion to existing warehouse storage
facility. The facility will be utilized for receiving bulk storage of mechanical materials.
UPS Pedricktown
KBD Group is providing general contracting services for approximately 1.2 million SF three building package.
Wilkerson Mill
KBD Group is providing general contracting services for approximately 1.2 million SF three building package.
Southwest 85 Logistics Center
KBD Group is providing general contracting services for approximately 1.2 million SF three building package.
Reliant Cass White Logistics
KBD Group provided general contracting services for Reliant Cass White Logistics, a three-building project in White, GA totaling 1.2 million square feet.
Hurricane Shoals
KBD Group is providing general contracting services
for a 350,000 SF speculative warehouse with site
package included.
JDA Polk Lane
KBD Group provided general contracting services for this single speculative warehouse building for Johnson Development Associates in Olive Branch, MS. This is a total 259,200 SF single dock side application on a 14 acre site.
Empire Distributors TI – Interiors
Empire Distributors TI | KBD Group performed interior construction for this beverage warehouse in Georgia.
Project Lake Groundbreaking
On April 6th, Tuesday morning, we were honored to stand with representatives to celebrate the groundbreaking ceremony of Spring Mountain Center’s future headquarters at Park 53 in Winder, GA.
The Edison Alpharetta
KBD Group provided General Contracting Services for this 104,000 SF speculative office building with common area and unattached clubhouse.
ATS Expansion
Expansion of a testing facility in Marietta, GA.
GE Transportation Locomotive Facility
KBD Group provided Design-Build services for the construction of a GE locomotive manufacturing plant.
Marukan Vinegar Plant
BD Group provided Design-Build services for the construction of a 77,000 SF new single story Vinegar Brewery plant with an office, production, and warehouse.
Toyo Tire Manufacturing Facility Phase IV
BD Group provided Design, Pre-construction, and General Contracting services for a 915,324 SF expansion to an existing mixing, tire preparation, tire building, tire curing, and warehouse areas.
Kubota Tractor Manufacturing Plant
KBD Group provided Design-Build services for a new 540,000 SF manufacturing plant with a two-story office, testing room, paint shop room, assembly line conveyer & paint line trench, bridge cranes, and hazardous material storage building.
Toyo Tire Manufacturing Facility – Phase III
KBD Group provided Design-Build services for a 838,743 SF tire manufacturing plant expansion.
Nichiha USA Manufacturing Facility
KBD Group provided Design-Build services for this, 413,300 SF cement fiberboard products manufacturing facility including an office building, a warehouse, a boiler building and a waste water treatment facility.
Colgate
Our scope included 14,000 SF of office build out (broken up into 4 separate offices).
Hettich Distribution Facility
KBD Group provided General Contracting services for Hettich, an international company based in Germany that designs and manufactures European hardware.
Riverside A
KBD Group provided General Contracting services tor this 653,484 SF concrete tilt panel shell with 127 dock doors and 4 drive in doors.
Kraiburg Office and Warehouse
KBD Group provided General Contracting services to a pre-graded site located at Hamilton Mill F.
Toppan Barrier Film Plant
KBD Group is providing Design-Build services for a barrier film manufacturing plant.
Kimoto Tech LC3 Renovation
KBD Group provided Design-Build services for the Kimoto Tech LC3 renovation project.
Empire Distributors TI
KBD Group provided General Contracting services for Empire Distributors TI Headquarters.
IDI Braselton Distribution Center
KBD Group provided General Contracting services for a 610,861 SF speculative shell building
IDI Hamilton Mill N
KBD Group provided General Contracting Services for this 912,522 SF Speculative Distribution Center located in Indianapolis, IN.
IDI Jefferson C
KBD Group provided General Contracting services for a 924,840 SF tilt panel warehouse with Ductilcrete slab.
Interstate West
KBD Group provided Design-Build services for a 55 acre site with a 762,253 SF speculative tilt-up warehouse
WESTRIDGE SPECULATIVE WAREHOUSE
KBD Group provided General Contracting services to a 46 acre site with a 612,511 SF speculative tilt-up warehouse
PFG Oakwood
KBD Group provided design/build service for this 175,000 square foot greenfield food service facility
Southwest 85 Logistics
The facility is a 40’ clear, 1,208,301 SF warehouse constructed of tilt-up concrete and steel structure.
Triangle Tire Manufacturing Facility
KBD Group is provided design services for this 1.86 Million SF tire manufacturing facility in Kingsboro North Carolina.






![Project-Oceans-Ecopol-2[1]](https://kbd.group/wp-content/uploads/2023/07/Project-Oceans-Ecopol-21-768x768.jpg)
![Project-Oceans-Ecopol-2[1]](https://kbd.group/wp-content/uploads/2023/07/Project-Oceans-Ecopol-21-2-768x768.jpg)
![Project-Oceans-Ecopol-27[1]](https://kbd.group/wp-content/uploads/2023/07/Project-Oceans-Ecopol-271-768x768.jpg)
![Project-Oceans-Ecopol-36[1]](https://kbd.group/wp-content/uploads/2023/07/Project-Oceans-Ecopol-361-768x768.jpg)
![Project-Oceans-Ecopol-38[1]](https://kbd.group/wp-content/uploads/2023/07/Project-Oceans-Ecopol-381-768x768.jpg)